Jul
1
to Jul 31
Approximately 8 working days
PROJECT DEADLINE AUGUST 11
5 days for new deck framing and decking
1-1.5 days for railing
7 days total
Plumber, Electrical & Tiling > build cabinet in shop
Return to install fixtures & cabinet
Has company August 5-10
Approximately 8 days plus 1-2 days for roofing
postponed for the moment
7-8 working days
2 days for existing deck finishing
1 day for screening
Demo bathroom, insulation, vapour barrier, framing including tub WEEK OF JUNE 22.
Plumber, Electrical & Tiling > build cabinet in shop
Return to install fixtures & cabinet